Which aspect is defined within the Project Brief?

  1. Project team roles

  2. Scope of the project

  3. Budget constraints

  4. Risk management strategy

The correct answer is: Scope of the project

The Project Brief is a fundamental document within the PRINCE2 methodology that outlines the critical elements of a project, serving as the foundation for its initiation phase. The correct answer focuses on the scope of the project, which is a key component of the Project Brief. The scope defines the boundaries of the project, outlining what will be included and what will be excluded from the project. This clarity is vital for setting realistic expectations and ensuring all stakeholders have a unified understanding of the project's objectives and deliverables. By clearly articulating the scope, the Project Brief helps to avoid scope creep, which can lead to project overruns and misunderstandings later in the project lifecycle. In contrast, while team roles and responsibilities, budget constraints, and risk management strategies are essential parts of project management, they are typically detailed in other specific documents, such as the Project Initiation Document (PID) or within various planning processes that follow the initial Project Brief.